on 05-01-2013 7:41 AM
Hello,
Question regarding the following:
I have a HU-managed warehouse where we store Handling Units containing multiple batches of the same material. When I create a pick-TO for one of the HUs, the system generates a TO-item for each batch. Because these batches are packed into one HU, multiple TO-items can refer to the same HU.
Now, I want to pick the full HU and propose the source HU as the destination HU. This works fine if my HU only contains one batch (and thus only one TO-item). However, when I want to confirm the TO with multiple items, the system does not propose a destination HU. When I assign the source HU as destination HU manually during confirmation, the system doesn't allow and the following message occurs:
Any idea how to solve this issue?
Thanks & regards,
Oliver
Hi,
Please refer SAP note # 829266 for your issue, it says that you cannot specify the source HU as the destination HU when you execute the stock removal of a mixed HU (HU that contains more than one quant).
Regards
Vijay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
9 | |
9 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.