Hello All,

As per Business requirement , we need to overhaul OVA8 for almost all Credit Control Areas.

We need to change value of Fields like:-Max.doc.value ,Number of days,Max.open.item %,Days oldestItem,Static & Dynamic Checks.

What Precautions do we need to take after changing /rearranging OVA8?

Do we need to run some Programs after config change?

Please advice.

Thanks,

Vikas

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Dear Vikas,

Please ensure the execution of RVKRED77, RVKRED88, RVKRED09 and RVKRED07; testing before transporting any changes to PRD server is must. Also, have a look at the following thread. Thanks.

http://help.sap.com/saphelp_45b/helpdata/en/93/743861546011d1a7020000e829fd11/content.htm

former_member186385
Active Contributor
0 Kudos

Hi,

Run the report RVKRED88 for simulating Reorganizing SD credit Data and

RVKRED77 for reorganizing

check these two as well along with Sai's report

regards,

santosh

former_member184080
Active Contributor
0 Kudos

Hi Vikas,

You have to run the report RVKRED09. Its advisable to do the complete test in Dev and QAS before moving changes in Production.

For more information below thread helps you.

http://scn.sap.com/thread/1274597

http://help.sap.com/saphelp_45b/helpdata/en/93/743861546011d1a7020000e829fd11/content.htm

Regards, Sai Krishna.