on 04-30-2013 10:41 PM
Hello All,
As per Business requirement , we need to overhaul OVA8 for almost all Credit Control Areas.
We need to change value of Fields like:-Max.doc.value ,Number of days,Max.open.item %,Days oldestItem,Static & Dynamic Checks.
What Precautions do we need to take after changing /rearranging OVA8?
Do we need to run some Programs after config change?
Please advice.
Thanks,
Vikas
Dear Vikas,
Please ensure the execution of RVKRED77, RVKRED88, RVKRED09 and RVKRED07; testing before transporting any changes to PRD server is must. Also, have a look at the following thread. Thanks.
http://help.sap.com/saphelp_45b/helpdata/en/93/743861546011d1a7020000e829fd11/content.htm
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Run the report RVKRED88 for simulating Reorganizing SD credit Data and
RVKRED77 for reorganizing
check these two as well along with Sai's report
regards,
santosh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Vikas,
You have to run the report RVKRED09. Its advisable to do the complete test in Dev and QAS before moving changes in Production.
For more information below thread helps you.
http://scn.sap.com/thread/1274597
http://help.sap.com/saphelp_45b/helpdata/en/93/743861546011d1a7020000e829fd11/content.htm
Regards, Sai Krishna.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.