on 04-30-2013 4:52 PM
When cost is booked to a parent WBS how the wbs budget can be supplemented using the budget in another WBS? The system sowing an error message as exctly the released busget is diff than the distributed one. How to solve?
Hi,
As per the standard process , we had to upload/Supplement the budget for the top WBS , and that budget amount has to be transferred/distributed to the child WBS and Release accordingly.
It hope it might resolve your isuue.
Regards,
vrkumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
first you have to transfer the Budget from lower level wbs to the parent level and than supplement the budget for parent level if required.just try and see if it works.
Regards
Ramakrishna
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.