When cost is booked to a parent WBS how the wbs budget can be supplemented?

Former Member
0 Kudos

When cost is booked to a parent WBS how the wbs budget can be supplemented using the budget in another WBS? The system sowing an error message as exctly the released busget is diff than the distributed one. How to solve?

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

As per the standard process , we had to upload/Supplement  the budget for the top WBS , and that budget amount has to  be transferred/distributed  to the child WBS and Release accordingly.

It hope it might resolve your isuue.

Regards,

vrkumar

Former Member
0 Kudos

Hi,

first you have to transfer the Budget from lower level wbs to the parent level and than supplement the budget for parent level if required.just try and see if it works.

Regards

Ramakrishna

Former Member
0 Kudos

hi,

sorry for the spell errors in the question.

yes ramakrishna, it is not working. when we take out the required budget from the child WBS where the parent WBS is allocated with cost(wrongly), the distributed budget and released budget contradicts!