on 04-30-2013 4:57 PM
Hi at all,
I've got an issue regarding ATP determination with BOM materials.
I have a material A with 3 components (B, C, D). Only BCD are relevant for ATP and picking, A is only relevant for price determination.
I am creating an order with delivery date 17.05.2013. Everything could be allocated, only a part of D is not available. That means that the order cannot be delivered due to the delivery group is not complete. The problem now is the fact, that even the main component is completely confirmed to 17.05.13 althoug 1 component is not available. That means that the order confirmation says that the goods could be delivered in time - although they couldn't...
Is there a solution only to confirm the main material, when the components are completely available?
Thanks
Chris
See SAP note 72688 which states:
If you want to change this behaviour, you can apply the modification in note 72688.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
As you are using Delivery Group, COMPLETE DELIVERY is only the option as in standard
regards,
santosh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This book has function to copy for ATP with BOMs:
Amazon.com: SAP Multilevel ATP eBook: Leo Egerev: Kindle Store
Thank you
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.