cancel
Showing results for 
Search instead for 
Did you mean: 

Scheduling Agreement - Change of account assignment group

Former Member
0 Kudos

Dear All

    Due to an error in our master data for the account assignment group in sales org 2 view the Scheduling agreement carried the data for the same. Now we have rectified the material master data for this Sales Org/ Distribution  Channel combination. How can I correct the scheduling agreement Item data already created ?

Regards

T N Ramanathan

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Shobha,

You can't change the account assignment group in Scheduling agreement -> item data- billing tab directly.Since it's grayed out.

you need to delete the line item and enter the same material again, it will show the correct(Newly changed) Acct asgnmt grp in Scheduling agreement. Or

Correct the Acct asgnmt grp while creating the billing document-> item deatil screen. In creation of billing document this option can be editable only.

Regards

Karthik

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi Shobha,

Please read the below link to know how to close this thread and why to close.

If the above is not working plese see the URl

http://scn.sap.com/community/support/blog/2013/04/03/how-to-close-a-discussion-and-why

Regards,

Karthik

Former Member
0 Kudos

Dear Karthik

    The issue has been closed by correcting the material master data and thenblocking the items in the Sales Order/ Schedule Agreement and creating new lines for the same items,

Regards

T N Ramanathan

Former Member
0 Kudos

How many documents have been affected? If the number is manageable, pl follow the above suggestion, If the number of affected documents are many,  you may need to go for table edit in SE16N. In VBAP table, enter the document numbers and edit the value in field VBAP-KTGRM.

Former Member
0 Kudos

Dear Pronojit

   Thanks for the reply. We have followed the 1st solution.

Regards

T N Ramanathan

former_member184080
Active Contributor
0 Kudos

Hi Shobha,

Hope your issue has been resolved. If so, please close the thread by updating the corrective action you have taken on this.

Regards, Sai Krishna.

former_member184080
Active Contributor
0 Kudos

Hi,Shobha,

As suggested by Karthik, its better to delete the line item and add it again. BTW, if you have already created delivery and waiting for billing then you have to do at billing level or reverse the transactions add do it again ( You can suggest both to client and let them decide).

Regards, Sai Krishna.

Former Member
0 Kudos

Dear Sai

    Thanks for the Input. Will suggest/implement accordingly.

Regards