Hello,

I have a situation of 2 plants(1 sloc each) managed under one warehouse.

When I do plant to plant transfer of multiple materials using MB1B (301mvt), system creates  as many PCNs as the no of materials in the material document.  So consequently there are respective no of transfer orders to be created.

I want to avoid this situation by having only one PCN per material document irrespective of no of materials inside.

How to accomplish this?

Thanks.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

In addition to the Jurgen reply check the additional data of PCN (LU03), you can see that the PCN is mapped to the combination of material document and item number. So it  is not possible to create single PCN for multiple items of material document.

Regards

Vijay

JL23
Active Contributor
0 Kudos

TRs and TOs, have a header and an item table, (LTBK + LTBP, LTAK + LTAP), but the PCNs have just one table LUBU, this table does not know any item number. So I think it is just technically impossible to get what you want.