on 04-26-2013 9:27 PM
Hi Satish,
There could be several explanations for your "duplicate" entries. One important field not shown in your picture is the Material Document number. I'm guessing that the 2 entries have different values there, perhaps suggesting that either the GR was done in two parts, or that the second entry is a re-posting following an initial cancellation that either didn't transfer or got deleted.
Regarding the transfer log, it depends whether you're referring to Transit or Declaration before GR. Take a look at programs /SAPSLL/API_IBDL_TLOG_DISPLAY or /SAPSLL/API_TIBD_TLOG_DISPLAY - I think those both exist in GTS 7.2.
Regards,
Dave
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Satish,
Sorry about that - I failed to read your title correctly; hence the inappropriate question!
I agree that it looks strange. I wonder if, for some reason, you managed to create 2 Customs Documents for the Delivery? Could you check table /SAPSLL/LEGREF in SE16, to see if there is more than one entry for the Delivery item? If so, copy the field GUID_MOBJ and use it to find each Customs Document in table /SAPSLL/CUHD. The answers might give you some clues.
Regards,
Dave
Hi Dave,
Not a problem.
Here are additional details. Our GTS is connected to two ERP systems. The scheduling agreement is created in one ERP system which transfers to GTS. The same scheduling agreement is also automatically created in the second ERP system and that flows to GTS as well. They both have the same number but coming from 2 ERP systems. Might this be causing the issue?
I think this is the reason for duplicate records but I'm looking for a way to instantiate that. Do you agree?
Thanks,
Satish
Hi Satish,
If the duplicates are being created by transfer from the second ERP system, then you should be able to see that in the /SAPSLL/CORREF entries for the linked Customs Documents that I mentioned above. Those entries include the field ORGLOGSYS - the original Logical System.
Regarding the automatic creation of the Scheduling Agreement in the second ERP system - is that a feature or a fault? If it's a feature, then you will need to prevent the transfer to GTS in that situation, or alternatively always specify the correct Logical System on the selection screen before attempting to create the Import Declarations.
Let us know how you get on.
Regards,
Dave
User | Count |
---|---|