Hi Experts,
Can any body tell me in detail which T code or procedure we have to use in SAP PS to perform the profitability analysis? We already have actual cost and revenues for the projects.
Hi,
In SAP you carry out Month end closing activities. In order to carry out this activity, you post all period based data on the project. Subsequently data relevant for Profitability analysis can be determined for the given period and then this data can be settled to COPA.
This data can be evaluated in the project information system or in Profitability analysis.
Refer SAP help for more details
http://help.sap.com/saphelp_erp2004/helpdata/en/7a/4c3aad4a0111d1894c0000e829fbbd/content.htm
Regards
Tushar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You can use the transaction code KE30 to get PA reports.
Regards,
Sudhakar*
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
If you wanted to see the final out results of COPA, you can use the KE24, input the record type 'I" and WBS element (billing element which was assigned to sales document).
At the same time is advaisable to understand the basics of Profitability Analysis and its deriving factors you need to discuss with your CO guy or read the help documents. In this regard you also need to understand the Result Analysis process and settlement of actual costs which is predecor process steps of Profitability Analysis (COPA) results. COPA is not mandatroy funtion to implement here.
Thanks,
Sudhakar
Message was edited by: Sudhakar Pappu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Sir,
Thanks to all of you for your quick response.here i would like to bring in your knowledge that i have already made the settlement of the actual cost and revenue to the cost center and PSG respectively.i am performing the results analysis as well in KKA2 but there message i am getting that "network act.belongs to business area 2000 and actual ignored". Now i have two questions?
1.How to rectify this inconsistency of the Business area?As WBS and some of the networks have different business area..cost has been posted to it and it is grayed out even if we try to change it in cj20n.
2.As you said, Results analysis is the predecessor for the profitability analysis.Could you please elaborate how it is linked with Profitability analysis?
really thanks as you have suggested to go through the Help and results analysis ,i am already in the process,But this will be a great help for me if you could hint me on these two issues.
Thanks in advance,
Regards
Ramakrishna
RA does not work cross-company code. Is looks like you have a NWA in one comapny code and the WBS element in another. You first need to settle the NWA actual costs to the WBS element (this will be a cross-company code posting) and then you can run RA on the WBS element and it will include all of the costs.
Once you have ran and saved RA you can perform the settlement to PA.
you can take report from KE30 t-code COPA based.
Regards,
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.