Planned order without resource

Former Member
0 Kudos

Hi All,

I have  two planned order in product view for same products. One planned order is having resource and other is not having.

Both have same valid source of supply updated.

Please suggest if this can be done by any means like order de-allocation and then re-scheduling etc.

This planned orders are created under PPDS segment.

Regards,

AC

Message was edited by: Amlan Chatterjee

Message was edited by: Amlan Chatterjee

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Amlan,

Was your issue resolved?

Regards,

Vinay

Former Member
0 Kudos

Hi Amlan,

From the screenshot you have attached looks like the order without operations(resources) are deallocated orders. The operations only appear in orders which are scheduled. If it is rescheduled you can see the operations correctly.

You can reschedule the orders by manually moving the orders in DS board or running a sequencing heuristics after adjusting the capacity.

Hope this helps.

Thanks,

Kiru

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Amlan,

Are you using alternative sequence ? If yes then check it, that may be the issue.

Regards,

Vishal