Getting BOM cost into the Project Cost Plan (CJR2)

Former Member
0 Kudos

Dear All,

In our current project,  we are creating cost plan on CJR2 transaction. We are also doing a BOM transfer via CN33 to network activities. Is there any way to copy these material costs from project to WBS plan automatically ?

Regards,

Öncü

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

If you are using network costing, the cost for all BOM components with cost relevancy indicator should come autamatically as planned costs.

I do not understand why you want to copy it. It can create duplicate planned costs.

Regards,

Mahendra

Former Member
0 Kudos

Make sure the components are cost relevent and they will be included in Network Cost Planning.  Then set the NW Order configuration properly for appened in OPSV.

"You can specify with the appended indicator how the plan values of the
order are included in the planning value of the respective WBS element for
combinations of the following:....."