Dear All,
Need experts suggestion on this issue of budget control failure.
Certain cases have been found in our system where the Production order
booked value is more than the released budget of the concerned
WBS.Incurrence reported in standard reports is more than the released
budget in such cases due to this reason.
We assume that budget control check has not worked due to some reasons
for these cases. We have not been able to find the root cause of the
problem.Only thing that we could find out is that in all these cases ,
WBS system status is ISBD.
The attachment shows one sample case where Production order booked value is
more than released budget.
For information the following configuration settings is available
for budget availability control in our SAP system
Activation type is 1 Usage ( In budget profile)
Tolerance Group is ++ (Tolerance Limit)
Availability control action is 3 with Usage 100.5 (Tolerance Limit) .
Request experts suggestions on this matter.
Thanks in advance.
Regards,
Vishal
Whenever the order cost exceeds the budget ,ISBD -insufficient Budgetting status is set,the configuration for availability control is fine. Please try reconstruct availability control and after reconstructing availability control update project data base using tcode CJEN
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear All,
Thanks for the suggestions.
We have been able to find the root cause of this issue through SAP note 801961.
As per above note system allows certain actual postings like revaluation, repostings, more than the released budget .
Above note corrections will restrict such postings if there is no available budget.
Regards,
Vishal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI,
Please check with the below mentioned SAP Notes for your reference:
178837 :Availability control: Assigned value Calculation
166394 :Tolerence Limits of Active Availability control
152571 :Composite SAP Note: Missing or incorrect Commitments .
And try to Restructure the project once with CJEN , followed by CJBN and OPSX.
Please reward me if its helpful to you.
Regards,
vrkumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Vishal
Is it working fine with other Orders? Please check and revert back
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
11 | |
6 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.