Need help on factory calendar set up

0 Kudos

Hi,

Need your help on factory calendar set up with following specification

(The business requirement is to make the last 3 business days as non workdays)This is required for each month and every calendar year till 2022. We need this calendar for execution of background job ,which should not execute on last 3 business days.

Req: We want a background job execution on all business days ,but don't want this this job execution on last 3 business days of each month.

Optional looking at: We would like to set up one factory Calendar  with exception of making last 3 business days as Non working  days ,So that when will assign this Calender in Background job ,Background job will executes as per Calender Business Days (ie  minus 3 last business days of month) .This set up is reqd for each month and year till 2022.

Please suggest if we can do this.

Regards

Vijay

Accepted Solutions (0)

Answers (2)

Answers (2)

Ranjith418
Contributor
0 Kudos

Hi Vijay,

FC should be created by ABAP team but you can follow the document attached. document is a word document change the format from txt to doc.

Thanks,
Ranjith

Former Member
0 Kudos

Dear Vijay,

You use transaction SCAL to create factory calendars.

Select -change icon.

Create a new calendar do not select any days save - select “Special rules”.

Define the rules

Press save and go back to Overview screen.

Click on the Calendar button to see what these dates look like in a calendar format.

Select calendar which created

schedule a new job

Best Regards,

Rathish.S