on 04-24-2013 2:25 PM
Hello Everyone!
I have the following situation :
The ATP is configured to priorize category during allocation process.
The material X from my sales order does not have any stock available.
It was created 2 production orders :
Both have the same configuration, one with category other not.
Production order 1 - 29/05 - with no category
Production order 2 - 29/04 - with category
Problem : The date proposed is 29/05, and the stock of production order 2 is compromised.
Someone have any ideas?
Thank you,
Christian Geronasso
Hello,
I just found out the solution.
After reorganize coverage strategy the production orders were selected correctly.
Thank you.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.