Error message in QA01

Former Member
0 Kudos

Dear all,

When we create an inspection lot manually (Trx. QA01) and maintain inspection start date / end date in such a way that they fall during weekends/holidays, then system gives a warning message saying "The start /end date of the inspection is not a valid workday".

But in our system for only one user this same message is appearing as error message. Because of this, the user is unable to maintain proper dates for some lots.

I checked the factory calendar assignments for different plants/users, it is all same.

We also copied the user details(for which error appear) from production server to development server and  analyzed, but surprisingly in the development server, the same user is getting only warning messages!!!

Can anyone share their knowledge why system is behaving like this.

Regards,

Pavan

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Its really strange to get error message in one server & only warning message in another.

Assumptions:

  1. In Production server, you have been using same plant for different users, still you are getting 2 different messages
  2. In development server, same kind of factory calendar has been assigned to the plant.
  3. You have not customized that message control as mentioned in this thread (http://scn.sap.com/thread/448492)

If all condition applies, then check with SAP by raising an OSS.

Answers (5)

Answers (5)

Former Member
0 Kudos

Dear All,

Thank you all for your replies.

I went to the user personally to check what is going wrong and found a classic case of human error !!!

User was always using save button to proceed ahead with the other processes in the transaction which was resulting in continuous Warning message, as the lot getting created was during weekends. He did not pressed 'Enter' button. Now it is clear to the user and he also now understands different types of SAP messages and their behavior.

Thanks again for all your help.

Regards,

Pavan

Former Member
0 Kudos

You need to check two thing-

1) Factory calender

2)In inspection type setting in material master(QM View) how many days are maintained.

Appart of that need to check message type setting in all the lower system.

Regards,

siddharth

Former Member
0 Kudos

Hello,

Please check the factory calendar maintained in your work center in Inspection plan.

former_member42743
Active Contributor
0 Kudos

Any chance this user works primarily in a particular workcenter?  You can assign calendars to the work center but I've never personally tested them on the QM side.

FF

former_member192897
Active Contributor
0 Kudos

For your information, you can set messages user specific..

All you need to do is define the message with different version and set the message type to E and assign the same to the user in user master record with parameter MSV.

Check whether the User was assigned the said parameter in User master record.

vivek_tembe
Active Participant
0 Kudos

Dear Pavan

1 - Please check all relevant user exits, user authorizations

      Compare transport lists for development and production

2 - Keep weekends/holidays working for factory calendar and ask user to create Inspection lot (QA01)

     Check the system behaviour

Regards

Vivek Tembe