Availabilty Control Budget- values Planned

Former Member
0 Kudos

Hi,

I  have a question to ask for you:

We have projects, with availability control active, which were planned, (annual and total). When projects are in ejecution , and has  actual values​​, compromised values​​, (PO and PR), performs the calculation of budget taking into consideration:

actual values ​​+ commitment values  + values ​​planned , then active availability control, limiting the amount of budget, taking plan values​​, as if they were already commitment.

We have analyzed the customizing, and we  didn't find if there is way, to avoid that in the calculation, the system does not take the planned values in the budget availability control calculation.

I have been clear in my query?

Thanks and regards!

Mariana

IM-PS Consultant

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hello Mariana,

Tik mark Indicator 'Planning'  for Network type in OPSC.

Also go throgh below mentioned thread.

http://scn.sap.com/message/13835998

Regards

Tushar