on 04-18-2013 3:04 PM
Hi all,
My problem is :
When in assigment block Approval, if f.e. i have only 1 step for approve. When i do approve there status of CR are not changed and still in To be approved.
Same with Rejected not switch
Can any one help?
Regards Dan
Hi Dan,
please check IMG activity 'Set Up Process-Dependent Status Control' in the area 'Change Request Management Framework'. there you define in which status the approval procedure should go in case it is rejected/approved and has not/already created follwo on documents.
Maybe you have created a ZMCR and not the customizing,
best regards,
Michael
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Solved,
Was missed 2 actions in ppf and additional backround actions.
It's because ZMCR was copied from SMCR and reconfigured before me.
So there was missed customization.
Now im still working with custom transaction copy of SMCG with approval block.
Reject is not working, approve is working strange ...
Regards Dan