  Hi all,

if we create a wbs element for equipment can allot budget amount for that equipment and planned hours/ budget hours.

-Balaji

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Balaji,

1As kumar said take the equipment as an work center and assign it to the activity in cj20n.Do the activity type price planning in kp26.Please check and revert back if any further details are required.in this way you can capture the cost of that equipment.

2.Create this activity under the WBS element and do the budgeting for this WBS element.

Regards

Ramakrishna

Former Member
0 Kudos

Hi Balaji,

As per your requirement :

1. You can create a wbs element for an equipment and allocate budget .

2. Cost Planing can be done.

Or with the Network Activity ,assign the work center by maintaining the cost per hour in KP26 .