Hello Experts,
I want to integrate Internal order to project system for Budgeting.
What are the step need to be follow.
Thanks & Regards.
Message was edited by: Mohamed Rafi - Search PS & CO forums.
Hi,
Internal Order is also having the same Budget functionality where PS is having .
If still required PS budget , PS module should be implemented where WBS structure would be defined. And then maintain WBS tab in Assignment tab of Internal Order , and we can assign the Budget in CJ30 Original Budget , Release Budget CJ32 etc, similar to KO22 and KO24 Budget & Supplement in Internal order.