BED, Edu cess and Hcess calculation

Former Member
0 Kudos

Please can someone tell me the method to calculate the BED, Edu cess and H cess amounts (CR/DR) on daily basis. Our client needs customized report and for this and the standard extraction procedure(j2i4) is not of any use.

Is there any other method to calculate the same.

Accepted Solutions (1)

Accepted Solutions (1)

kailas_ugale
Active Contributor
0 Kudos

Hi,

check report J2I6 and J2I9

Regards

Kailas

Answers (1)

Answers (1)

Former Member
0 Kudos

For plant, you need to update RG23A and C part 2 registers daily using J2I5 and then download them in excel using j2I6. You can easily find the values in each column on date basis.

For depot, you need to update RG23D register daily using J2I5 and then download them in excel using j2I6. You can easily find the values in each column on date basis.