SAP - PS Status triggered by actual date

Former Member
0 Kudos

I am looking for some help on the above situation.

Is it possible to have a WBS Element that has a status triggered on a set date.

For example:

If I wanted the status to be released automatically on a future date, 4/27/2013, is this capable of being done automatically on this date?

Thanks

GK

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Gareth,

As per your requirement such functionality is not available in the standard system.

We can schedule the Future date planning among the options:(  Scheduling Type) :  Forward, Backward,Only Capacity requirement, Current date, Forwards in time, Backwards in time. But we cant set the status Release automatically as per the future date, We had to set the status manually among the options: Never, From Release, Immediately. ( Procurement Type ) .

Regards,

vrkumar

Former Member
0 Kudos

Can a date trigger a user status with an enhancement?

Answers (0)