Best practice for uploading WBS BoM from external systems

Former Member
0 Kudos

Hi

We are using the project system (PS) for our engineer to order (ETO) products. The engineering is done in external engineering systems. The design is built progressively. We are looking for the best practices to upload these progressively built BoM's in SAP as WBS BoM's. Creating and maintaining the WBS BoM's manually is not an option as volume is huge and prone to mistakes.

Pl suggest the best ways to upload (create / modify / delete) the WBS BoM's from external engineering systems.

Thanks

Vivek

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Vivek,

The Open Project System (Open PS) suite provides an interface between the Project System and any other external system. Regardless of whether you are using a laptop or a palm pilot, whether you happen to be at a customer site or on the road between appointments, it gives you the freedom and flexibility to access individual parts of the Project System from your external system and carry out important business transactions.

Open PS for Microsoft Project / Open PS for Palm.

Regards,

vrkumar