Dear Gurus
We are running SRM7.01 with Classic scenario deployment. We do not use productIDs/Material Master in SRM: Only adhoc or catalog items.
We have a need to introduce over-delivery tolerance for our confirmations in ECC.
Could you please advise how this can be done for classic if no material masters are used when the PO gets created in ECC?
Thanks
Ian
Hi Ian,
You could set up Tolerance Limits for Confirmation. Please find below SCN threads for your information;
http://scn.sap.com/thread/766681
https://scn.sap.com/thread/1838294
Hope this helps.
Thank you
Ritesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ritesh
Thanks for the response. The threads you supplied mostly talks about confirming in SRM. We are running in Classic and wish to receive in ECC thru MIGO. We do not have any material IDs in SRM so create adhoc line items or from catalogs. We do specify Material Groups / Prodcut Categories.
I need to set up config in ECC for the SRM Classic POs. I did see something about being able to set tolerances against Material Groups where no material ids specified, but cannot find anything.
Any idea?