on 04-09-2013 6:48 PM
Hi All
I have following scenario
Sales Contract(VA41)>>Sale Order(VA01)>> Invoice(VF01)
At sales contract we assign WBS element manually (in Account Assignment Tab) and then creating Order and do billing.
We have requirement in Report CN41N
Proj.rev.plan should be Sales Contract Value(VA41) and Act. revs should come through Billing (VF01).
Is there any way to achieve this requirement.
I am new to PS and I am sorry if this is a silly question.
Revenue planning will be done via planning profile either from quotation or sales order.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
If you are looking automatic update of revenue from Quotation (VA41), please tick the check box against " From Quoatation".
Tushar: Rebecca looking from Quotation and not from Sales Order.
Thanks,
Sudhakar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello ,
Check in OPSB if Planning profile is maintained in Project. Also ensure that 'From Sales order' checkbox is tiked in Automatic Revenue Planning.
Refer Revenue section under sap help
http://help.sap.com/saphelp_46c/helpdata/en/aa/96853478616434e10000009b38f83b/frameset.htm
Regards
Tushar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
pl check CN41 and hopefully it meets your requirement.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.