on 04-08-2013 8:07 PM
Dear All,
I am having a requirement wherein at a particular location product A is replaced by both the products B and C.To meet this requirement , have defined the 1:n product interchangeability(not sure whether this has to be defined to meet this requirement). Have released the Interchageabilty group and assigned to the model.
Even after this definition , product substitution is not taking place at this particular location. Could somebody help me in regarding this issue.
Note:
1. After defining the 1:n relationship my expectation is that a common planning package number has to get created in the product master A,B and C.which is not happening. Is this a reason for product substitution not happening at this factory location.
2. If i am defining a product - product substitution ( normal case) , product substitutuion is happening at this particular location.
Regards,
nandha
Are you using forward or Full interchahgeability?
Try to use A > B and in second row define B > C
It will work.
Vipul Shah
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.