Work center hours

nureya
Participant
0 Kudos

Hello All,

I have a user question. We have a work center XYZ in SAP PM. How can i find out the planned hours of that work center for a particular period?Is there any Tcode for that?

Help appreciated,

Sylvia

Accepted Solutions (0)

Answers (2)

Answers (2)

nureya
Participant
0 Kudos

If i want for a particular year, what tcode should i use? this gives for a week or month. I want for the complete year for a particular work center, what are the planned hours?

Former Member
0 Kudos

You are not going to create PM Orders for whole years, it will be only for maximum another one month. Once the PM Order gets generated, then only you can see the Capacity Load required.

Change the Option Profile for Start Date & End Date. It will give you for the required period.

Production - Capacity Requirements Planning - Evaluation - Profiles - Define Options Profile

Former Member
0 Kudos

Based on the Planned hours maintained in PM Order against operations, you can check the total Planned hours in CM01 (in %), CM02 (in actual UoM) & CM03.

Note: Please use Enterprise Asset Management space for PM related queries.