laimonas_bindokaitis3
Participant
0 Kudos

Hello guys,

I have a problem with budget control behavior.

All limits are set for hard stop in case of any overrun of wbs cost budget.

Now,

KSV5 is run - actual allocations. And system responds with warning but not error of exceeded budget.

Question -

How to make KSV5 act as any other actual posting with error in case budget is exceeded ?

Please help guys.

Thank you.

Regards,

Laimonas

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Laimonas,

your enquiry is described in SAP note 865855:

Regards, Gordon

laimonas_bindokaitis3
Participant
0 Kudos

anybody ?

former_member209919
Active Contributor
0 Kudos

Hi,

Have you review the settings in SPRO --> PS--> Costs --> budget ---> define Tolerance limits?

If you display a warning they are configured here, then you should check why error message is not configure whem budget > 100%

regards