on 04-08-2013 8:24 AM
Hi,
In
the SNP planning books, we are using forecast consumption, the consumption as
such is working ok
However,
somethimes we are moving sales orders and deliveries from one month to another
with a user exit macro; and create a delta with them in a time series key
figure taht is copied to another area.
However,
at this moment, we face an issue with the withdrawal quantities. As soon as the
sales orders become a delivery and then are becoming a Good issue, the
withdrawal quantity is deducted on bucket level (months) from the forecast
requirments.
This
can be seen in table /SAPAPO/DP_SCHED and /SAPAPO.DP_HEAD. However, is there a
way we can see these withdrawal quantities (goods issues) in APO on a normal
date (with a date stamp) This should then happen before it goes to the DP_SCHED
table?
Regards,
Tommy
I don't understand the problem.. what is the issue?
Yes once you do a PGI the forecast stays consumed. The system keeps track of the withdrawal quantities also. Do you have a CIF integration model for the requirements reduction?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.