while Cif ing what is first CIFed from R/3 to APO ? do we hav a protocol

former_member205751
Participant
0 Kudos

while Cif ing master data to APO  which master data  is first CIFed from R/3 to APO ? do we hav a protocol  .....say like material master has to be cifed first then PV in the form of pds or ,work centres,

so what needs to be cifed first ??

good to have your inputs

Accepted Solutions (1)

Accepted Solutions (1)

former_member189901
Contributor
0 Kudos

Hii Rahul,

Please go through the following SAP Help Link.

http://help.sap.com/saphelp_scm50/helpdata/en/74/d67237902ae147e10000009b38f842/content.htm

Hope it'll give you a clear idea.

Regards

Debashis

Answers (1)

Answers (1)

sourabh_jain66
Active Contributor
0 Kudos

Hi Rahul,

Normal protocal which is followed by the most is:

first CIF different configs like ATP config. --> plant --> material --> work centers --> PPM / PDS --> after this you can choose among other objects to be CIFed.

Logic here is to transfer objects which are required to transfer other objects first.

For more detailed information on this, you can follow SAP recommended sequence.

Rgds

Sourabh

sourabh_jain66
Active Contributor
0 Kudos

hi Rahul,

Did this answers your query, please let me know if you are looking for some other information.

Rgds

Sourabh

former_member205751
Participant
0 Kudos

thanks sourabh......you put clarity in my mind ...for long this was a confusing subject which comes first and which comes last

babu_kilari4
Active Contributor
0 Kudos

Hello Rahul,

Thumb rule :- Master data should be CIFed at first followed by the transactional data. Your CIF setup of RIMODGEN / RIMODAC2 should also have the same sequence. Close the thread if you have received the relevant answers from the SCN practitioners.

Babu Kilari