Commitment budget check during PM order creation (IW31)

Former Member
0 Kudos

Hi Experts,

We would like to have commitment budget check during IW31. How can this be achieved. We need to manually enter the commitment item manually in assignments. Can we have commitment budget check for plant maintenance orders ?

Please let me know how to achieve this.

1 REPLY 1

iklovski
Active Contributor
0 Kudos

Hi,

PM order creation does not open a commitment in FM; thus, no budget is checked.

Regards,


Eli