How the sales order requirement is given for the MRP run in MTO scenario? ( Likely in MTS scenario through MD61 Tcode we give the requirement)

Hi gurus

How the sales order requirement is given for the MRP run in MTO scenario? ( Likely in MTS scenario through MD61 Tcode we give the requirement)

Regards

Sandeep

Former Member replied

Hi,

The setting in procurement tab of sales order has to be done for each and every sales order.In SD customizing you can configure CN (No MRP by default) and on need basis change it to CP or by default system will create sales order by CP and on requirement this can be changed to CN.

CSN

1 View this answer in context

Helpful Answer