Hello,
We are using Block planning with CDP (SCM 5.0) for our Paper Roll manufacturing business. Here the Orders are created during ATP/CTP process and are scheduled in respective block’s per Order requirement date and available block capacity. Also MTS orders are being created and scheduled accordingly in respective block’s.
ISSUE : -There are instances where we are observing that the Orders are moved from the existing block (ABC) to another (XYZ).This behavior is happening even when there are NO planners in the system doing any drag & drop and NO order entry are being entered in the system . Also checked for NO planning batch job running in APO/ECC.
Performed few check’s to decipher the trigger for this order movement via few log’s /report’s available in APO (/SAPAPO/C7, C3, /SAPAPO/RRPEVAL…etc.) but couldn’t figure out the cause.
We have the time stamp / period when the order actually moved (Eg: Ord moved b/w 10 ~ 11PM) ,but having this info as input wanted to see if we can square up on what had triggered /caused the order movement in APO Planning board during this stipulated time.
Appreciate your valuable input's.
Regards
VJ
Hii VJ,
Just check in the Log(/sapapo/rrplog1) and find out how the order has been moved. If the orders are moving either its rescheduled by some heuristic or some interactive planning etc...
So this will give the clear idea, here you can put the time limitation also.
Hope it'll help you..
Regards
Debashis
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.