on 03-01-2007 1:25 AM
We wanted to create a subcontract PO for a sales order. The components in the subcontract PO is in unrestricted stock. Can we move as unrestricted ?
No BOM is used, componenets are manually entered.
After GR, will the componenets be visible ( as it will be cosumed at GR) if so can what status is it in - unrestriced or sales order?
Hello Kumar,
<b>Incase you components are in un-restricted stock / Own stock and final product is sales order stock</b>
Please correct if my assumption is not as per your requirement.
- You have sales order for material (i.e. TV set)
- You have components (Picture tube, cabinet, switches) in unrestricted stock.
- You want to send this components to subcontracting vendor for making final product (TV set)
In this case,
- Create Sales order for TV set
- Create purchase order for TV set with Account assignment category "C" with item category 'L' (check if A/C cat C and Item categor L combination is available)
- Mention the components in the purchase order on material data tab
- Issue the component using 541 mvt type
- Receive the final product with MIGO with 101 mvt type, in background it will consume the componenet materials.
Now after MIGO the final product will be shown as special stock for sales order.
<b>Incase, your components are sales order stock, not in un-restricted stock then proceed as follow:</b>
Subcontracting is also possible in conjunction with sales order stocks and project stocks. The subcontracting orders are account-assigned to a sales order or a WBS element. Thus, the components are not transferred (using a transfer posting) to the "stock of material provided to vendor" but are directly withdrawn from the sales order stock or the project stock at the time of the goods receipt. The material manufactured is also posted to the sales order stock or to the project stock. The cost of subcontracting is then debited to the sales order or WBS element.
http://help.sap.com/saphelp_erp2005vp/helpdata/en/4d/2b90b043ad11d189410000e829fbbd/frameset.htm
Hope this helps.
Regards
Arif Mansuri.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Arif
But my specific requirement is they want visibility of the components after we recieve the subcontract PO, and the components has to be consumed in the sales order ( when they Godds Issue agaonst sales order).
They are using seperate SLOC at subcontractor location and we move the components using SLOC to SLOC movements.
Hope am clear.