on 04-02-2013 8:08 PM
HI SAP Gurus,
I have a PO and the values in the header tab "Status", following values are displayed:
Ordered | 15,772,820.15 |
Delivered | 14,520,850.69 |
Still to deliv. | 1,251,969.46 |
Invoiced | 562,511.48 |
Down paymts | 308,265,840.63 |
Now the purchase order is still open and open value is USD 1,251,969.46. The same value is expected in CJI5 report for this PO only.
Whereas the value displayed is USD 7094417.18.
We are not sure why the value is displayed wrongly in CJI5 report. Need your input.
PS:
1. FM is active in Controlling area.
2. Executed correction programs RKANBU01, RKACOR04, but the values remains same in CJI5 report.
3. Commitment management is active in controlling area.
Also run RKACOR10 and then run CJEN. Hope it helps.
Check the table COOI too for value type 22. Check the value displayed at the table level. This should give you some pointers.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI Gokul,
Thanks for your reply. I have already executed these programs, but the problem still exists. Also, to note here, the PO's which have multiple account assignment creating this error.
PO's with single account assignement and assigned to same WBS element does not display any error in CJI5.
Any further input on this, will be really helpfull.
Thanks and regards,
Narender.
Hello,
I have the same issue than you with service PO with multiple account assigment, I have reported the issue to SAP.
I could fix wrong PO executing report RKANBU01 and it fixed the wrong omiitments.
But I reproduced the issue in new PO in development and I am pending from a SAP answer.
If the report doesn't fix your commitment implement if you don't have impemented these 2 OSS notes (i had to implemented)
680078
1494533
Please share your results!
Regards
Hi All,
The issue with in my case is that, the PO has multiple account assignment. And the distribution was different on WBS element in PO and while creating the SES's, user has put different distribution.
And hence the values for those WBS was open for which in PO the planned values are more whereas in SES's, the amount was less.
Consider the example as below:
PO Value | SES value | ||||||
A | B | C | D | A1 | B1 | C1 | D1 |
Percentage | PO Value | Each WBS allotment | SAA | Percentage | SES value | Each WBS allotment | Comparing Column C and C1 |
30 | 12000 | 3600 | 1 | 38 | 12000 | 4560 | |
32 | 12000 | 3840 | 2 | 32 | 12000 | 3840 | |
38 | 12000 | 4560 | 3 | 30 | 12000 | 3600 | 960 |
The CJI5 report will display 960 as in column D1 which is an error from business point of view whereas from SAP point of view its correct.
Hence, there is no error in SAP.
Thanks and regards,
Narender.
Hi,
i had same type of issue earlier. Then i raise the issue to SAP. As the part of the solution they had asked me to implement OSS note- 1427643, 1541767, 1616873 and after then execute RKANBU01.
Regards
Deepak
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Try to run the above correction programs RKANBU01, RKACOR04, and after that followed by the execution of CJEN and CJBN for the project .
Then the Wrong Commitment values in CJI5 will be updated accordingly.
Regards,
vrkumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.