Hi,
I followed the blog http://scn.sap.com/community/pi-and-soa-middleware/blog/2006/06/22/xi-playing-with-the-file-adapters....
Issue I am facing is that I am creating two files through two interface mappping in interface determination of ID. When I run the above BPM specified flow process, it always move to deadline branch even though files are being created successfully and sxmb_moni also showing successful acknowledgement for both files.
After thorough investigation I figure it out that it s happening due to creating two files. When i deleted one interface mapping from interface determination of ID, the process run successfully and accurately. This had helped me to understand the issue,
but how can i fix the issue as it requires to create two files as sender service (BPM) and receiver system of both the files are same.
Hi Anwar,
i am also working out on this,can you please explain me in BPM how the SEND, RECEIVER,SWITCH STEP has been configured.
thanks in advance
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
10 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.