We have done cost planning for the project via base planning object.
BPO contains material, service and equipment.
Our requirement is after assigning the base plan in each WBS.
If we change the material rate in one BPO, it will automatically update the value in each WBS where we assigned.(cj40).
Please do the need ful
Regds
Srikumar. S
Hi,
By standard system its not possible to achieve this kinf of functionality like auto update but z-development is the best option to get it. so check with abap there are some standard FM to update the cost and masterdata in ps module so abap will code including such FM then you can achieve.
Regards,
sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Srikumar Sethu,
i have the same problem I want automatic update of project or WBS element when BPO is updated.
Please let me now if you have a solution
Regards Pierluigi Sivitelli
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.