Hi Experts,
I am new to CIN. Please help me.
I received goods from subcontractor, In MIGO finished goods and bom components it is showing completed, we fully at a time. Subcontracting challan completed, when i am checking J1IF12, for two components GR qty showing zero and other all materials GR qty showing fully received.
for these two materials i checeked in J1IF12, reversal qty showing quantity. I also checked in MB51, for these materials 541 o mvt type showing with negative quantity
please help me, how to resolve this
Discussion moved. Please use Internationalization and Unicode for CIN related queries.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Issue resolved .
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Maintain below entries in CIN for allowed movement types
MVT. Grp. MvT S
0001 122
0001 541
0002 101
0002 322 O
0002 542 O
0002 543 O
0002 544 O
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Pls check in table J_1IEXCDTL what the qty updated against the field "GR quantity".
Also pls ensure that the settings for movement type groups is as per the below OSS note.
1808300 - Error 8I574 - Material XXXXXXXXXX is not assigned fully, short by XX.XXX
Regards,
Rajasree
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
What is the challan status? Is it completed or reversed.?
Possibility may be challan is reversed and without doing recredit, it is completed.
Thanks
ig
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.