Enhancements for Easy cost planning

Former Member
0 Kudos

Dear All,

I have a project based make to order scenario.There I have to do easy cost planning.I am doing so by adding the line items.While doing so the value is getting picked from the mbew table.I want the price to be updated from qbew table.Please let me know how to do so.Is there any enchancement available for this.

Thanks.

Regards,

Shivali Thakur

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Mahendra,

Actually the scenario over here is project specific.There will be no purchase which will not be project specific.The material master will not get updated as it is with account assignment q.Therefore How to do easy cost planning in such a scenareio.?I am a bit confused.

Thanks.

Regards,

Shivali Thakur

Former Member
0 Kudos

I think it is not possible to pull the values from QBEW in the ECP. However I recommend you create record in MBEW (by manually putting the price in material master or using MR21. This can be the simplest way to achieve it.

Regards,

Mahendra

Former Member
0 Kudos

QBEW will have specific entries for each WBS and material combination.

Out of that which one you want to choose?

Any specific reason you want it to pick up from QBEW instead of MBEW.