check at item level WBS.

Former Member
0 Kudos

Hi All,

         I am facing some issue regarding  wbs element at item level.there is no check at putting wbs element at item level user can give any wbs element as per its liking.Is there any possibility that we can give validation of wbs at item level.Looking for your fruitful advice.

The coding mask of the wbs is as per sales organisation.If different WBS is provided then it affects cost of another project.

Regards

Arya Nath

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Dear Arya,

As per the process the coding mask of WBS will be defined by the PS module itself, but that WBS no will be shared to SD team for booking the Revenue of that  particular project WBS. If we want to restrict you can develop validation from sales point of view by mapping Sales order with one project /WBS range.

But as per the PS point of veiw there is milestone Billing functionality ( DIP Profile ) has to be defined and to be integrated with both project and Sales order, for PS & SD integration .

And through CNS0 is for project delivery.

I hope it might be helpful inf.

Regards,

vrkumar