on 03-25-2013 8:31 AM
Dear Gurus,
Resources of capacity category 0014 (Storage resource) are not transfered to APO, and in the log it states that capacity utilization needs to be maintained, the field of capacity utilization is not present in the capacity screen for resource category 0014.
Any solutions???
Regards,
MaX
Hi Max,
Have you tried maintaining the "APO Resource" screens in ECC? In the capacity header screen, you can find this menu button and it has a field to maintain the capacity utilization (APO Resource capacity header - Standard Capacity tab).
Thanks,
Rajesh