on 03-23-2013 3:38 PM
Hello Experts,
No Alerts are generating & Displaying at Alert monitor after background job run ..??
Alerts are generating at interactive planning and displaying and Alert not generating through backgorund job.. Alert monitor setup done properly.
checked the all logs and looks fne (SLG1 , SM21 , Job log and Spools and Done the consistency check for MPOS & Planning area.
Please provide us an hints...which might leads this kind of inconsistent state.
Thanks in Advance..!!
Ravi Kumar .A
Maybe you have some default macros not included in background job? Default macros run automatically in interactive planning, but may not run in background run ...