on 03-22-2013 6:26 AM
Hello Experts,
I have configured ChaRM for my maintenance landscape and I have done retrofit part for moving the transport request from manitenance landscape to project landscape. But there is a confusion how to do the cutover with the help of ChaRM. How do I define the route so that the cutover from mainetenance to project landscape can be done without any problem.
Maintenance landscape [MND -> MNQ -> MNP]
Project landscape [PJD -> PJQ]
Thanks in advance
Regards
Sunny
1175098 - Change Request Management retrofit configuration |
http://scn.sap.com/people/dolores.correa/blog/2009/08/27/change-request-management-scenario-
Latest retrofit blog
http://scn.sap.com/docs/DOC-38698
I hope above will help you to clear the doubt
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI Prakhar,
the below link is saying you are not authorized i am able to open all other docs, any help?
User | Count |
---|---|
83 | |
23 | |
11 | |
9 | |
8 | |
5 | |
5 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.