on 03-20-2013 2:26 PM
Hello Everybody
How can we accommodate time based Safety stock in CTM?
Regards
Rachel
Hi Rachel,
You to make the SNP time based key figure available for CTM in SPRO.
SPRO--> supply chain planning--> Multilevel supply and demand Matching --> Make SNP key figures available.
And assign the planning area in CTM profile.
BR
Thamizh