on 03-18-2013 9:37 AM
Hello,
I'm using PS to create the requirements for the materials. To create the requirement I use the planned Ind Requirements for WBS instead of reservation for a WBS element . And then The MRP create the planned order for this WBS element segment . Then use PP to create the production orders and MM to create the purchase orders.
Then I would like to use the CO46 transaction to Analyse the Order progress repport fo the project . But When I use the standard profiles for CO46 I can't found the sames materials & planned orders that were created by the MRP . Has somebody any experience using this CO46 transaction to execute this repport for a single project. In fact I expect to have all planned orders & purchase Requisitions created for my project.
thanks in adavanced for your help
Beatriz Ocampo
Hello,
In fact I realise that the CO46 show only the order repport for the reservations created for the project. But instead of reservations for WBS element I'm using the Planned Independent Requirement for the project . That means I manage the separate planned order for the WBS segment when the MRP runs for thoses materials . For each Planned Ind Req Created for a material in a wbs element I obtain a planned order ( order type PR) in the MRP results and in MD04.
The thing is in CO46 for my project I expect to have the order repport for the planned orders generated by the MRP for the planned Ind requirement .
If execute CO46 by planned order or by production order I obtain order repport that I expect but if I execute CO46 by project SAP does not show me any line. Somebody knows if is possible to use this transaction for the PLanned ind requirement created in the project ??
Thank you in advanced for your help
best regards,
Beatriz Ocampo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Check MRP4 view of material missing in CO46 list. Field 'Individual /collective' requirement should not be 2. It should be 'Blank' or '1'. Also check Production order material master first, if ind/collective =2 , then all material under production order will not appear in C046.
It is kind of deactiuvate 'Project stock/Procurment' setting... hence they don't appear in Co46... Acoount assignment of thes PO will be blank & Project will not appear in Purchase order.
It has nothing to do with Profiles on Co46 tcode.
Hope it helps,
JAtin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.