Dear experts,

i have user status profile-wbs level which contains 4 statuses.

  1. 1. init- project creation stage
  2. 2. bugp- budget assignement allowed only
  3. 3. bugr-budget release only
  4. 4. exen-wbs release and other business
    transactions....execution.

in opuu- under res/pur req field we have '2'. i.e from release.

now after creating project my status in wbs would be init. at
this stage if user add a non stock material with code or without code....and in
component overview if by mistake he selects 3 in res/pur req field i.e
'immediatly' a pr is getting genarated. and po can be done. but at the time of
migo it will prevents from business transaction. however i have already
forbidden mat pur requisition' trasaction in init status. so it wont allow to
raise pr for manually created pr/outside pr (procurment of mat). or it wont
allow to release the wbs. because the sequense is from init status to bugp
where user has to do cj30, then bugp to bugr- in that cj32 and finally user has
to set pass on from bugr to exen to release the wbs for execution.

now from cj20n, in init status if user creates non stock
material by giving 3 in component overview. system takes that and creates pr
without budget.

how to avaid this? which business transaction do i need to
forbid from creating pr at this status.

please guide

prashanth.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Search the forum. This query has been discussed innumerable times in the forum. I am damn sure you will also land up with a solution if you search the forum

Regards,

Gokul