on 03-15-2013 7:50 AM
Hi All,
We are facing below issue.
I have created SO in CRM and replicated to ERP fine, when I try to change the partner my unit of measure is getting change like MD to PC automatically for all material.
Our ABAP person checked and find out The change in condition unit is during the interface of data between CRM and ERP. This was seen when the distribution lock was removed and saved. CRM condition unit became PC and ERP condition unit remained MD.
The issue seems due to ERP side. This is because at debugging the incoming data from ERP to CRM in the middleware exchange program, we saw that the incoming data already contained the changed condition unit ie PC.
Please help me to provide some information.
What is SD user exits which would have changed the condition unit.
Thanks.
Preddy.
Dear
Is it happening only for one condition or for all condition types?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
MD id Man days and PC piece.
And for your information we have find out the issue why it is changing form MD to PC.
In Unit of measure MD ISO code and PC ISO code we maintained C62, when i remove ISO code C62 in unit of measure MD then it works fine.
We have around 12 unit of measure in my project for all we have maintained ISO code C62.
Is there any problem if i remove the ISO code in MD.
Thanks,
Preddy.
User | Count |
---|---|
99 | |
11 | |
10 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.