I am facing problem in CNE1.

In configuration we defined measurement method Cost proprtional for PLAN & Degree of processing from CO for Actual.

But when we run CNE1 & click on assign method to objects it is taking Different Measurement method (for both Plan & Actual) i.e SAP Standard SAP 0-100

What could be the reason?

Please suggest.

Regards,

Fayaz.

Accepted Solutions (0)

Answers (1)

Answers (1)

sanjeevc
Active Contributor
0 Kudos

have you checked cj20n activity progress tab wherein may be you have assigned measurement method as told. sap 0-0100

Regards,

sanjeev

Former Member
0 Kudos

Hi Sanjeev,

Yes in activity also below are the details mainained.
measurement method Cost proprtional for PLAN & Degree of processing from CO for Actual.

Regards,

Fayaz.

Former Member
0 Kudos

Hi All,

Any suggestion?

Regards,

Fayaz.