on 03-11-2013 8:31 AM
Hi All,
Am getting Error "Planning elements XXXXXX already exists" while creating multiple items in PPM.
but if i debugg items created successfully.
Please give me any suggestions.
thanks and Regards
Dhanu
Hello Dhanu,
Implement SAP Notes 1831826 and 1601893.
Best Regards,
Brendan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Are you creating a cProject at the same time than the Item?
It seems a problem creating the cproject. I suppose you have configured a cproject template linked to your item and it is not being created properly.
Check how your cProject template is created and the name of the project/phases/tasks in the template and how the phase and task ID are created.
I had a similar problem because I named the task with these code X123 X124 and the value as so long then the system created task X12 ( instead of X123) and then had to create X124 but created again X12 and the system informs the same error message as yours.
Regards
Hello,
I think your problem is beause you have configured to create another object at the same time than the item.
- Check if you are trying to create a cProject ( project, phase, tasks) and check if it is being created correctly
or
- Check if you are trying to creat a Project in PS ( project, WBS...) and check if it is being created correctly.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
10 | |
5 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.