Hi,
I want to know whether it is possible to trigger mail alerts to the respective Person Responsible at different Budget Tolerance limits. (e.g. To trigger mail alerts upon reaching both 75% and 90% utilization)
Thanks,
Sujith.
Hi Sujith,
you need to select availablity control action 2 with the usages of 75% and 90% in usage in % column.
Also check the below thread similar as your requirement.
http://scn.sap.com/thread/3243715 |
Regards,
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sanjeev,
The limitation is that, I can not maintain multiple tolerenace limits against a same action item (e.g. I can not mention action item 2 against both 75% and 90%. Only posibility is that to config action item 1 against 75% and action item 2 against 90%)
Is there is any alternative to accomplish this requirement?
Thanks,
Sujith.
Dear Sujith,
As per your requirement is to send the Bugdet Exceed Error mail to concerned person for both 75% and 90 % with same activity of 2 ( warning with Mail to Person Responsible) .( 90% .)
I suggest to create another activity 4 with ( warning with Mail to Appliacant No ) 75 % .
I hope this might be suits for your requirement.
Regards,
vrkumar
Dear VR Kumar,
As per my understanding we can not create additional Activity Types. By defualt SAP has 1 - 3 Activity Type against Budget availability control:
1 Warning
2 Warning with MAIL to person responsible
3 Error message
Please do let me know is my understanding is wrong and there is a way to create cuztomized activity types.
Thanks,
Sujith
Hi Sujith,
As per the standard default Availability activity types are 3 only , but as per your business requirement , if you requires two different options of 75% and 90 % with same activity functionality means, i.e I suggested better check with Zdevelopment table ( V_TBPFD) for creation of new 4 activity with same functionality of sending mail ( But maintain Applicant ,inspite of Person Responsible )Warning with MAIL to Appliacnt ) , to avoid duplication from 2 activity .
So Applicant field also has to be maintained in project /WBS, along with Person Responsible.
1. Applicant : ( 4 75% Warning with MAIL to Applicant.)
2 Person Responsible: 90% ( 2 Warning with MAIL to person responsible )
Regards,
User | Count |
---|---|
102 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.