Hi,
My Landscape is 100(Dev)-> 200(Qlty) -> 300(Prod) . ChaRM works perfectly for this landscape.
Now I have one more client 110 in development system. All my unit testing happens in 110 Unit testing client.
Transport requests are created in 100 client. How can I copy the Transport requests to 110 client for performing unit test.
Manually I can use SCC1 for copying the transport request from 100 client to 110 client.I don't want to do it using SCC1 manually.
In ChaRM Urgent change process how can I handle this copying of transport requests. Are there any actions available for handling this or any option in tasklist
Regards
P Kumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Jansi,
Thanks. My only question is will I be able to copy the TRs from 100 to 110 client thorugh ChaRM.
Transports ( Workbench & Customizing) will be always moved from 100 to 200. But 110 is an additional client for Unit Test, where Transports will be copied from 100 . The source client of all TRs will be 100 only.
Is there any way by which I can copy the TRs from 100 to 110. May be by some action or in Task. or some batch job.
Regards
P Kumar
User | Count |
---|---|
92 | |
11 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.