Hi,
User tries to post MIGO 01 for material with QM activated.
For earlier PO, inspection lots are created at MIGO.
For another PO, the inspection lot is not created. The materials goes to unrestricted and the status GR doc has the value 6-Insp. lot already created from previous document.
What could be the error?
Thanks,
Neelima
Try activating inspection type 01 in material master.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check you Inspection type settings.
There is an option in inspection type to specify under which conditions a new inspection lot is created. The options are (roughly, as far as i remmeber without checking):
1. Every new batch
2. Onec per material/vendor
3. Every material document item.
Set this field to 'for every material document item'.
This means every GR item for that material will create a inspection lot, even if an open inspection lot is created ( even for the same batch )